Scheduling guide

OFCI vs CFCI: how owner furnished equipment changes the schedule

By Firat Acar, Founder and CEO, Plan104 · November 7, 2026

On data centers and other equipment heavy projects, the owner often buys major equipment directly and hands it to the contractor to install. That split changes who controls the delivery dates, and it changes how the schedule has to be built. This guide explains the terms and how to schedule owner furnished equipment.

The terms

  • OFCI, owner furnished, contractor installed: the owner buys the equipment, and the contractor receives, sets and installs it.
  • CFCI, contractor furnished, contractor installed: the contractor buys and installs the equipment.
  • OFOI, owner furnished, owner installed: the owner buys the equipment and installs it with its own vendors.

On data centers, OFCI often covers long-lead items such as generators, switchgear, UPS modules, transformers and cooling equipment, because owners buy them in volume across several sites.

Why OFCI matters for the schedule

With CFCI equipment the contractor controls the purchase order, the submittals and the ship date. With OFCI equipment those dates belong to the owner and the owner's vendors, but the contractor's installation, energization and commissioning still depend on them. If an OFCI delivery is late, the work that follows is late, and depending on the contract the contractor may be entitled to more time.

How to schedule OFCI equipment

  • Show each OFCI package as its own delivery milestone, coded to the owner as the responsible party.
  • Link deliveries to receiving, setting, installation, energization and L1 to L5 commissioning.
  • Include factory witness testing (L1) and ship dates from the owner's vendor schedule.
  • Track the float on each OFCI delivery every update, so the team sees how close it is to the critical path.
  • Record actual delivery dates and conditions on the day they happen.

When an OFCI delivery slips

Model the new delivery date in the current schedule update and measure its effect on completion with a time impact analysis. Because the delivery is coded to the owner, the impact is clear and documented, which makes the request for time easier to support.

How Plan104 helps

Our scheduling consultants build OFCI and CFCI equipment into the CPM schedule with clear responsibility, track delivery float every update and prepare the analysis when a delivery moves. See our data center construction scheduling services.

Frequently asked questions

What does OFCI mean in construction?

OFCI means owner furnished, contractor installed: the owner buys the equipment and the contractor receives, sets and installs it.

What is the difference between OFCI and CFCI?

With OFCI the owner buys the equipment and controls its delivery dates. With CFCI the contractor buys and installs it and controls the whole process.

Who is responsible when OFCI equipment arrives late?

The owner usually controls OFCI delivery dates, so a late delivery is often treated as an owner caused delay. The contract decides, and a time impact analysis shows the effect on completion.