Scheduling guide
By Firat Acar, Founder and CEO, Plan104 · November 7, 2026
When a project finishes late, the question is not only how late, but why and who is responsible. Schedule analysts answer it with a handful of recognized methods. This guide compares the most common ones and when each is used.
Compares the baseline schedule with what actually happened. It is simple and easy to explain, but it shows where the job finished late more than why, and it does not account for changes to the plan along the way.
Adds delay events to the baseline schedule and measures how much the completion date moves. It is quick, but it ignores progress and the real sequence of the work, so it is often challenged when used on its own.
Inserts a fragnet, a short sequence of activities that represents a change or delay, into the schedule update in effect just before the event, and measures the effect on completion. It is the standard method for requesting time when a change happens. See our time impact analysis services and our guide on how to prepare a TIA.
Splits the project into periods, usually between schedule updates, and measures how the critical path and completion date moved in each one, using the schedules the team actually worked to. It shows when each delay happened and who drove it, which makes it a strong choice for claims and end of project reviews.
Starts from the as-built schedule and removes delay events to see when the project would have finished but for those delays. It relies on a detailed as-built record and careful logic.
These methods are described in AACE International Recommended Practice 29R-03 for forensic schedule analysis and in the Society of Construction Law Delay and Disruption Protocol. The contract and the quality of the schedule records usually decide which one fits.
Every method is only as strong as the records behind it. On projects that use the Plan104 construction operations platform, RFIs, change orders, site photos and progress are documented against the schedule activity on the day they happen, so the evidence is already there when an analysis is needed.
On active projects the time impact analysis is the most common method for requesting time. For claims and disputes after the fact, windows analysis is widely used.
A TIA looks forward and models one change with a fragnet. A windows analysis looks back over the whole project, period by period, using the contemporaneous schedule updates.
AACE International Recommended Practice 29R-03 for forensic schedule analysis and the Society of Construction Law Delay and Disruption Protocol are the most widely referenced.